污水处理厂扩建工程的调试培菌方案选择及实施 被引量:3

Choice and Implement of Debugging Bacterial Schemes for Expansion Project of Wastewater Treatment Plant
下载PDF
导出
摘要 介绍了无锡市城北污水处理厂扩建工程的设计概况,并针对该扩建工程,提出了在调试方案选择时,应充分考虑实施的可操作性、经济性及对现有生产的影响。系统介绍了对所选方案的实施,主要包括调试、试运行前期准备、培菌、联动调试及培菌成熟,并最终达到可投产等阶段工作。 The eapansion project for chen -bei wastewater treatment plant in Wuxi was introduced, and it was brought forward that the operability, economy and effects on current production should be fully considered. The implementation of the chosen plan was introduced systematically, including debugging, preparation for trial operation, bacterial cultivation, linkage debugging, bacteria cultivated maturely and finally the process of putting into production.
出处 《污染防治技术》 CAS 2008年第1期112-115,共4页 Pollution Control Technology
关键词 污水处理厂 扩建工程 调试 培菌 wastewater treatment plant expansion project debugging bacterium cultivation
  • 相关文献

参考文献3

共引文献10

同被引文献3

引证文献3

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部