摘要
介绍了无锡市城北污水处理厂扩建工程的设计概况,并针对该扩建工程,提出了在调试方案选择时,应充分考虑实施的可操作性、经济性及对现有生产的影响。系统介绍了对所选方案的实施,主要包括调试、试运行前期准备、培菌、联动调试及培菌成熟,并最终达到可投产等阶段工作。
The eapansion project for chen -bei wastewater treatment plant in Wuxi was introduced, and it was brought forward that the operability, economy and effects on current production should be fully considered. The implementation of the chosen plan was introduced systematically, including debugging, preparation for trial operation, bacterial cultivation, linkage debugging, bacteria cultivated maturely and finally the process of putting into production.
出处
《污染防治技术》
CAS
2008年第1期112-115,共4页
Pollution Control Technology
关键词
污水处理厂
扩建工程
调试
培菌
wastewater treatment plant
expansion project
debugging
bacterium cultivation