为了确保隧道后续施工的安全和洞口段初期支护质量,结合新五块石一号隧道工程概况,详细介绍了隧道出洞的施工方案,并就浅埋偏压隧道出洞时所遇见的一些问题做一探讨,提出了相应的解决措施,为类似隧道施工提供参考。
To assure the safety of tunnel succeeding construction and the quality of opening original supporting and combined with the new five stones No. 1 tunnel project general situation, it specific introduces the tunnel unkennelling construction program, discusses the problems that happened in shallow burying bias-voltage tunnel unkennelling, and puts forward the corresponding solving steps, this supplies reference to the construction of similar tunnel.
出处
《山西建筑》
2008年第12期311-312,共2页
Shanxi Architecture
关键词
隧道
边仰坡防护
爆破
监控量测
软弱围岩
tunnel, side slope protection, blast, supervision and measurement, soft fender