摘要 自动发电控制(AGC)是调整电网频率与有功功率、保证电网安全经济运行的重要措施之一。文中介绍蓬安县电网与四川省电网实时挂网连接时,应用水电厂计算机监控系统高级应用软件AGC功能,依托马回扩建电站实现了与四川省电网之间实时控制上网负荷(电量)的生产需求。在电力大区联网和电力市场运营的新形势下,提供了提高电网AGC运行和专业技术管理水平的实例。 Automation generation control (AGC) is one of the important measures to adjust the frequency or active power of power grids and to ensure their safety and economy. AGC, witch is an advanced applied software function in the SCADA of the Mahui Hydropower Station, is applied to realize real-time control of the power grid load through Peng' an Grid which is linked to the Sichuan Province Grid. In the new situation of network interconnection and electricity market, this is an example of improving the operation and management level of AGC of power grids.
出处 《水电自动化与大坝监测》 2008年第2期11-13,20,共4页 HYDROPOWER AUTOMATION AND DAM MONITORING
关键词 自动发电控制 负荷调节 实时控制 AGC load regulation real-time control
  • 相关文献

参考文献7

二级参考文献27

  • 1冯永青,张伯明,吴文传,李尹,孙宏斌,林鄂华.电力市场发电机组检修计划的快速算法[J].电力系统自动化,2004,28(16):41-44. 被引量:37
  • 2郑延海,张小白,钱玉妹,徐田.电力系统实时安全约束调度的混合算法[J].电力系统自动化,2005,29(12):49-52. 被引量:39
  • 3张粒子,黄弦超,舒隽,陶文斌.配电网检修计划优化模型设计[J].电力系统自动化,2005,29(21):50-52. 被引量:38
  • 4李刚,程春田,蔡建章,蔡华祥.云南电网日调度计划编制系统[J].大连理工大学学报,2006,46(1):111-115. 被引量:1
  • 5[2]杨小煜,沈松林,吴杏平,等.华北、东北联网后电网AGC及其考核的实现[J].电网技术,2001,25(7):60-62.Yang Xiaoyu, Shen Songlin, Wu Xingping et al. Implementation of automatic generation control in North China power grid and its assessment after interconnection of North China power grid with Northeast China power grid[J]. Power System Technology, 2001,25(7): 60-62.
  • 6周京阳,于尔铿.能量管理系统(EMS) 第5讲 自动发电控制[J].电力系统自动化,1997,21(5):75-78. 被引量:69
  • 7LEOU R C.A flexible unit maintenance scheduling considering uncertainties.IEEE Trans on Power Systems,2001,16 (3):552-559.
  • 8DA SILVA E L,SCHILLING M T,RAFAEL M C.Generation maintenance scheduling considering transmission constraints.IEEE Trans on Power Systems,2000,15(2):838-843.
  • 9ZURN H H,QINTANA V H.Generator maintenance scheduling via successive approximation dynamic programming.IEEE Trans on Power Apparatus and Systems,1975,94 (2):665-671.
  • 10SAWA T,FURUKAWA T,NOMOTO M,et al.Automatic scheduling method using tabu search for maintenance outage tasks of transmission and substation system with network constraints//Proceedings of IEEE Power Engineering Society 1999 Winter Meeting:Vol 2,Jan 31-Feb 4,1999,New York,NY,USA.Piscataway,NJ,USA:IEEE,1999:895-900.

共引文献128

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部