平胜大桥体系转换施工控制的关键技术 被引量:29

Key technologies of construction control in system transformation for Pingsheng Bridge
下载PDF
导出
摘要 针对自锚式悬索桥体系转换施工期的受力和变形特点,系统地总结和提出吊索张拉方案(含鞍座顶推)确定的六原则。以此原则为基础,探讨平胜大桥(世界上第一座独塔自锚式悬索桥)吊索张拉的可能方案,给出推荐方案。针对自锚式悬索桥吊索张拉方案中各施工步实施及其控制的共性问题,讨论吊索张拉方案中各施工步的实施控制原则和实施方法,给出建议。平胜大桥按推荐方案、建议的施工步实施控制原则和实施方法进行吊索张拉和鞍座顶推施工和控制,高效、高精度地达到了预期目标。 In view of the mechanical and deformation characteristics in the construction period of a self-anchored suspension bridge with system transformation, six principles for determination of the suspender tension and saddle pushing procedures have been proposed. The Pingsheng Bridge is the first self-anchored suspension bridge with single tower in the world. Based on the proposed principles, the possible suspender tension and saddle push procedures for the Pingsheng Bridge are investigated. A reasonable procedure is suggested. According to the common problems in each construction control step for a self-anchored suspension bridge, control principles and implementing methods for each construction step are discussed and suggestions provided. The suspender tension and saddle pushing constructions are carried out. The objective is reached with high efficiency and high accuracy.
机构地区 长沙理工大学
出处 《土木工程学报》 EI CSCD 北大核心 2008年第4期49-54,共6页 China Civil Engineering Journal
基金 国家自然科学基金(50778024) 广东省交通科技项目(200633)
关键词 自锚式悬索桥 吊索张拉方案 施工步 张拉控制原则 先粗后精分步张拉到位法 self-anchored suspension bridge suspender tension procedure construction step suspender tension control principle tension procedure step by step from roughness to precision
  • 相关文献

参考文献3

二级参考文献4

  • 1尼尔斯J吉姆辛 金增洪译.缆索支承桥梁[M].北京:人民交通出版社,2002.252-253.
  • 2Klein J F.瑞士日内瓦湖上的新型悬索桥方案[A].哥本哈根IABSE学术会议论文集[C].1996.
  • 3颜娟.自锚式悬索桥[J].国外桥梁,2002(1):19-22. 被引量:51
  • 4楼庄鸿.自锚式悬索桥[J].中外公路,2002,22(3):49-51. 被引量:29

共引文献25

同被引文献143

引证文献29

二级引证文献148

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部