摘要
介绍了准格尔黑岱沟露天矿短期生产计划编制系统及其模型的建立,提出煤矿床地质模型建立过程中的一种考虑各向异性改进的距离幂次反比估值方法,以及图形编辑、计划区算量方法.其估值方法对沉积形成的倾斜矿床及煤层尖灭点估值是有效的,短期生产计划系统模型具有实用性和先进性.
The short-period production plan system for Heidaigou Surface Mine and model building are introduced, in this paper.It's put forward an improved distant power inverse estimating value method considering having different character in every direction in the process of building the coal mine deposit geology model,the graphics edition and the method of calculating volume for plan area. This method is effective to estimate the deposited slanting mine bed and point of thinning out. This short-period production plan system model is practical and advanced.