以南水北调渠道项目S26标军营沟排水渡槽T梁后张法预应力张拉为例,采用理论计算和施工实际相结合的方法,详细阐述了张拉工艺和张拉参数的计算。
Taking prestressed post-tensioning on T-shaped beam of Junyinggou drainage flume in South-to-north Water Transfers Project's canal as an example, and using the method by combining theory computation with practice, the article introduces the tensioning technique and tensioning parameters in detail.
出处
《山西水利科技》
2008年第2期73-74,共2页
Shanxi Hydrotechnics
关键词
预应力
张拉工艺
参数计算