复杂软弱岩层大巷的稳定性与支护方式研究 被引量:1

Study on Stability of Complex Soft Rock Tunnel and Its Support Ways
下载PDF
导出
摘要 复杂软弱岩层大巷具有变形量大、难支护、围岩持续变形破坏的工程特征,实践表明,现有支护难以控制。通过对不同支护方式的数值分析,提出了全封闭支架+全断面松动卸压以及二次锚杆支护的支护方式,数值分析结果表明,新支护方式下应力集中程度减小,高应力区向围岩深部转移,有效控制了围岩的剧烈变形。现场试验证明,新支护方式通过适度让压和锚杆支护强化围岩的作用,充分发挥了锚杆与围岩的整体力学效应,使围岩变形达到稳定的时间明显缩短,保证了巷道的稳定,具有显著的技术经济效益。 The complex soft rock tunnel has engineering characteristic of large deformation, difficult to support and continuous distort destroys, practice indicates that it is difficult to control with existing support. By analyzing different support way numerically, proposed the way of fully enclosed support coupled with full face loose relieving, as well as bolt supporting for second time. The results of numerical analysis show no stress concentration occurred, and the high stress regions are converted into the deep areas after applying new support way, which efficiently control the severe deformation of surrounding rocks. It has been carried out in situ that the stability of rock can be achieved through fully exerting the mutual action between the bolt with wire mesh and the surrounding rock with new way, and the interval of reaching stability state of entry surrounding rock is obviously reduced, which possess remarkable technology and economic benefit.
出处 《煤矿安全》 CAS 北大核心 2008年第4期17-20,共4页 Safety in Coal Mines
基金 国家自然科学基金资助项目(50774077,50574089) 全国博士学位论文作者专项资金资助项目(200760) 教育部新世纪优秀人才支持计划资助(NCET-06-0475)
关键词 复杂软弱岩层大巷 应力转移 全断面松动卸压 二次支护 complex soft rock tunnel stress - transfer loose relieving of full face secondary support
  • 相关文献

参考文献6

二级参考文献85

共引文献2434

同被引文献7

引证文献1

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部