高温季节泵站泵送混凝土施工的温控防裂方法研究 被引量:9

Research on Temperature Control and Crack Prevention of Pumped Concrete of Pump Stations Built in Summer
下载PDF
导出
摘要 泵站裂缝是一直困扰工程界的"疑难杂症",裂缝的出现使人们对于泵站能否安全运行产生很大的疑虑。针对这种情况,将冷却水管技术应用于泵站施工期,并且采用"表面保温+内部水管降温"的双重防裂措施。以上方法在南水北调淮安第四泵站工程中得以应用,获得了良好的效果,迄今为止在已经完工的部分尚未发现裂缝,可以为类似工程建设提供借鉴作用。 Since cracks make people feel doubtful about the safe operation of projects, cracks in pump stations are a problem that has been perplexing the field of engineering. To deal with the problem, the author puts forward the application of pipe cooling to the structure of pump stations. In addition, a dual measure including superficial preservation and pipe cooling for crack prevention is proposed. With the application in one pump station, the above methods proved to be effective. So far, no cracks have been found in the completed part of the structure. The result shows that the method can be applied to similar projects.
出处 《中国农村水利水电》 北大核心 2008年第4期105-107,共3页 China Rural Water and Hydropower
基金 国家自然科学基金资助项目(5057080) 水利部科技创新重点项目资助(SCXC2003-10) 河海大学院士学科发展基金资助(HHUYS003)
关键词 泵站 温控防裂 泵送混凝土 冷却水管 仿真计算 pump station temperature control and crack prevention pumped concrete cooling pipe simulation calculation
  • 相关文献

参考文献4

二级参考文献6

共引文献195

同被引文献55

引证文献9

二级引证文献33

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部