摘要
对综采工作面收尾期间漏顶成因进行了分析,通过过漏顶区的实践,总结出了过综采工作面漏顶区的有效方法。
The causes of top leakage during the end session of mining in fully mechanized coal face were analysed. On the basis of production practice, the effective method of getting across the roof leakage area was summed up.
出处
《中国矿山工程》
2008年第2期32-35,共4页
China Mine Engineering
关键词
综采工作面
收尾期间
过漏顶区
煤壁打钢针
技术实践
fully mechanized coal face
the end session of mining
the roof leakage area
a pin of coal wall
technical practice