摘要
景洪水电站右岸工程碾压混凝土于2004年2月8日开始施工,至2005年10月25日结束,累计完成碾压混凝土61.8万m3。景洪水电站右岸工程碾压混凝土施工的全过程,包括原材料及配合比选择、工艺试验、分层分块、施工布置及入仓方式、施工工艺及组织、温控措施等,对高温多雨地区碾压混凝土施工有一定的参考价值。
The RCC construction of the right-bank works of the Jinghong Hydropower Station was started on February 8, 2004 and completed on October 25, 2005, with the accumulated RCC volume of 618 thousand cubic meters. The whole process of RCC construction of the right-bank works of the Jinghong Hydropower Station such as the selection of raw materials and mix proportion, technique tests, zoning and blocking, construction arrangement, placement modes, construction techniques, construction organization, and temperature control measures, etc., has certain reference value for the RCC construction in high temperature and rainy regions.
出处
《水力发电》
北大核心
2008年第4期55-58,共4页
Water Power
关键词
右岸工程
碾压混凝土
施工
景洪水电站
right-bank works
RCC
construction
Jinghong Hydropower Station