桩静载荷试验快速法与慢速法对比研究 被引量:13

Study on method comparison between quick and slow load in pile static test
下载PDF
导出
摘要 通过对54根管桩静载荷试验快速法与慢速法对比试验研究,找出了在各级荷载作用下,快速法与慢速法沉降差异规律及快速法与慢速法分别得出的极限承载力差异规律;得出了将快速法静载试验下的沉降及单桩极限承载力修正成慢速法静载试验的沉降及单桩极限承载力的公式;提出了适应天津地区管桩的快速法静载试验方法。 On the basis of the method comparison study between quick and slow load static test from 54 pipe piles, the settlement difference rule between quick and slow load in every grade was obtained, the difference rule of the ultimate bearing capacity from quick and slow load test was achieved, the conversion formula of the settlement and the ultimate bearing capacity from quick load to slow load test was derived. And a quick load test method of pipe pile suitable for Tianjin area was presented in this paper.
出处 《水文地质工程地质》 CAS CSCD 北大核心 2008年第3期35-38,共4页 Hydrogeology & Engineering Geology
关键词 桩静载荷试验 快速法 慢速法 沉降 承载力 pile static test quick and slow load method settlement bearing capacity
  • 相关文献

参考文献5

  • 1JGJ106-2003.建筑基桩检测技术规范[S].北京:中国建筑工业出版社,2003.
  • 2.JGJ94-94.建筑桩基技术规范[S].北京:中国建筑工业出版社,1995.25-50.
  • 3.GB50007-2002.建筑地基基础设计规范[S].北京:中国建筑工业出版社,2002.168-169.
  • 4DB29-20-2000.岩土工程技术规范[S].北京:中国建筑工业出版社,2001.
  • 5JTJ2202-83.港口工程桩基规范[S].北京:人民交通出版社,1983.

共引文献19

同被引文献57

引证文献13

二级引证文献29

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部