摘要
在迎峰度夏期间,为配合新建头沟110 kV变电站启动,需将纪头110 kV线路进行接引,在进行了可行性论证后,把纪营110 kV变电站5号母线与隔离开关带电接引作为专题进行调研并实施,首次完成了母线三相带电接引工作,确保了纪头110 kV线路的如期投运。
In order to cooperate with start-up of new Tougou 110 kV substation during the summer peak, Ji- Tou 110 kV transmission line needs to be connected with grid. After feasibility study, on-line connection of No. 5 busbar and disconnector in Jiying 110 kV Transformer Substation was investigated and implemented. This three-phase busbar on-line connection had completed and ensured the successful operation of Ji-Tou 110 kV transmission line on schedule.
出处
《华北电力技术》
CAS
2008年第5期23-26,共4页
North China Electric Power