摘要
介绍了杭甬线输气管道工程压气站变频器室的负荷特点,对涡旋式制冷机组方案与溴化锂一体化机组方案进行了详细的技术、经济分析论证,通过对工程的特殊要求和具体情况的分析、比选,得到了溴化锂一体化机组方案是最适合的制冷方案。
Introduced are load characters of transducer room at compressor station in Hangzhou-Ningbo Gas Pipeline project,analyzed are vortex refrigeration unit and integrated potassium bromide unit technically and economically,analyzed and compared are special requirements and specific conditions of the project,result shows that integrated potassium bromide unit is a refrigeration option suitable for the project.
出处
《天然气与石油》
2008年第2期4-6,共3页
Natural Gas and Oil
关键词
变频器室
压缩式制冷
吸收式制冷
涡旋式制冷机组
溴化锂一体化机组
Transducer room
Compression refrigeration
Absorption refrigeration
Vortex refrigeration unit
Integrated potassium bromide unit