摘要
简要叙述2号高炉鼓风机同步电动机(48000kW)由于受突发外来冲击高压定子绕组对地击穿的故障分析机理,以及处理对策和决定依据。
An analysis is made on the mechanism of the earth breakdown of the stator winding arising from the impact of a sudden external high voltage on the synchronous motor(4800kW)for No.2 BF blower,and a basis for the counter measures are put forward as well.
出处
《宝钢技术》
CAS
1997年第5期12-14,共3页
Baosteel Technology