67m高3200t重钢结构人字塔架的安装

Installation of 67m High and 3200t Steel Herringbone Tower
下载PDF
导出
摘要 天津慈海桥摩天轮工程中,水上型钢箱柱体人字塔架截面大、高度高、质量大,吊装焊接施工困难。采用分段整体吊装、空中组焊的方法成功完成人字塔架安装,介绍了具体施工流程和安装施工中采取的主要措施。最后对塔架合拢后轮轴梁和塔顶位移进行监测。结果标明,位移精度满足要求,证明了该方法切实可行。 Section steel box-column water herringbone tower was used in giant wheel of Tianjin Cihai Bridge. The herringbone tower is difficult to lift and weld because of its large cross section, high altitude and heavy weight. Integral multi-section lifting with high-altitude welding method was adopted to install herringbone tower. Construction process and measures were introduced. Displacement of axle wheel and top tower were monitored after the tower closure. The results show that the displacement can reach the requirements, and the installation method is feasible.
出处 《施工技术》 CAS 北大核心 2008年第5期100-104,共5页 Construction Technology
关键词 钢结构 塔架 分段吊装 施工技术 位移监测 steel structure tower multi-section lifting construction technology displacement monitoring
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部