摘要 A self-developed elasto-plastic finite element program was used to analyze the construction sequence of high rock slope's stabilization in a coal-coking plant, and the result was compared with that employing the ultimate equilibrium method. Based on the results of finite element analysis, the stress contour graphs and displacement vector graphs at different construction steps were obtained, and the behavior of the slope during stabilization construction process was analyzed quantitatively. Based on the analysis of safety factors of three different schemes of stabilization and two different construction schemes, the assessment of stability and bracing design of the construction process were performed. The results show that the original reinforcement design is improper; the stability of the rock slope is controlled by a developed structural plane, the stability factor after excavation is less than 1, and the free surface should be braced in time; for stability, the construction sequence should adopt that bracing follows excavation step by step up to down; the local slide occurred during the construction process agrees with the dangerous slide determined by the numerical analysis, which proves the validity and rationality of the adopted method. A self-developed elasto-plastic finite element program was used to analyze the construction sequence of high rock slope' s stabilization in a coal-coking plant, and the result was compared with that employing the ultimate equilibrium method. Based on the results of finite element analysis, the stress contour graphs and displacement vector graphs at different construction steps were obtained, and the behavior of the slope during stabilization construction process was analyzed quantitatively. Based on the analysis of safety factors of three different schemes of stabilization and two different construction schemes, the assessment of stability and bracing design of the construction process were performed. The results show that the original reinforcement design is improper; the stability of the rock slope is controlled by a developed structural plane, the stability factor after excavation is less than 1, and the free surface should be braced in time; for stability, the construction sequence should adopt that bracing follows excavation step by step up to down; the local slide occurred during the construction process agrees with the dangerous slide determined by the numerical analysis, which proves the validity and rationality of the adopted method.
出处 《Journal of Harbin Institute of Technology(New Series)》 EI CAS 2008年第2期188-193,共6页 哈尔滨工业大学学报(英文版)
基金 Scientific and Technological Support and Guidance Plan Projects of Zhejiang Province(Grant No.2008C23019)
关键词 岩石斜度 路肩 模拟技术 可塑造性 high rock slope stability stabilization construction process simulation elasto-plastic FEM method
  • 相关文献

参考文献7

二级参考文献80

  • 1李献民,王永和,律文田,肖宏彬.土工格栅加固路桥过渡段的动测试分析[J].中南大学学报(自然科学版),2004,35(5):860-864. 被引量:17
  • 2朱合华,桥本正.盾构隧道管片接头衬砌系统的两种受力设计模型[J].工程力学,1996,13(A03):395-399. 被引量:28
  • 3朱合华 侯学渊 等.基坑开挖反馈设计分析.软土地基变形控制设计理论与工程实践[M].上海:同济大学出版社,1996.163-170.
  • 4卓家寿.复杂空间结构非线性分析的分区混合元程序包[A].姜弘道主编.水工结构工程与岩土工程的现代计算方法及程序[C].南京:河海大学出版社,1992.15~37.
  • 5朱合华,工程力学,1996年,10卷,增刊,395页
  • 6朱合华,软土地基变形控制设计理论与工程实践,1996年,163页
  • 7杨林德,岩土工程问题的反演理论与工程实践,1996年
  • 8桥本正,日本第30 回土质工学发表会讲演集,1995年,1693页
  • 9郑颖人,地下工程锚喷支护设计指南,1988年
  • 10陈祖煜.土质边坡稳定分析[M].北京:中国水利水电出版社,2003..

共引文献1593

同被引文献6

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部