三沪直流工程导线舞动防治措施研究 被引量:1

Study on Galloping Prevention in San-Hu DC Transmission Project
原文传递
导出
摘要 鉴于导线舞动主要由覆冰及其截面形状、风速及其方向、导线系统的自身参数3个方面的因素形成,有针对性地从气象条件考虑,避开易于形成舞动的覆冰区域与线路走向;从机械与电气的角度,提高线路系统抵抗舞动的能力;从改变与调整导线系统的参数出发,采取各种防舞装置。结合三沪直流工程的实际情况.提出采用防舞器及转动线夹式间隔棒的综合防舞措施。 Galloping is caused by three major factors, such as covered ice and its cross-section shape, wind speed and its direction, and conductor's own parameters. Considering weather conditions, the transmission line should avoid icing region and direction that tend to form galloping; from mechanical and electric point of view, galloping resistance of the line system should be increased; by changing and adjusting line parameters, antigalloping measures should be taken. Using San-Hu DC project as an example, galloping prevention method that uses damper and spacer with rotating clamp is proposed.
机构地区 中南电力设计院
出处 《电力建设》 2008年第6期26-29,共4页 Electric Power Construction
关键词 三沪直流工程 导线舞动 防舞措施 San-Hu DC transmission project galloping galloping prevention measures
  • 相关文献

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部