摘要
介绍大顶子山航电枢纽工程采用粉细砂冲填筑坝的试验研究,为工程大面积施工提供了依据,并对同类工程的设计施工具有一定的指导作用。
The experimental research on dam building by filling fine silt in Dadingzishan Navigation-Power Junction project is described. The research provides a basis for large-area construction and may guide the design and construction of similar engineering
出处
《水运工程》
北大核心
2008年第5期42-45,49,共5页
Port & Waterway Engineering
关键词
水力冲填
施工方法
试验
观测
hydraulic filling
construction method
experiment
observation