以汤溪河特大桥顶推施工为工程背景,探讨了顶推时间的选择、顶推方案的选择、施工监控方案的实施等方面的内容,为类似桥梁施工和监控提供了宝贵的经验。
Taking the Tangxi river Bridge pushing construction as the project background,it discusses the choices of pushing time,pushing plans and construction,so as to offer precious experiences for similar bridge construction and supervision.
出处
《山西建筑》
2008年第16期298-300,共3页
Shanxi Architecture
关键词
连续刚构桥
顶推施工
施工监控