直孔水电站大坝溢流面采用HF高强耐磨混凝土,消力池表面采用硅粉高强耐磨混凝土。为保证混凝土施工质量,对原材料进行了严格控制,对配合比进行了优化,并制定了一系列浇筑和养护措施,高强耐磨混凝土质量达到了合同及设计的要求。
The overflow surface of the dam for Zhikong Hydropower Station used HF high strength and abrasion-resistant concrete and the surface of the stilling pool used high strength and abrasion-resistant siliceous concrete. In order to guarantee the construction quality of concrete, the raw materials have been strictly controlled and its mix proportion has been optimized. A series of measures of pouring and curing have been taken so that the quality of high strength and abrasion resistance concrete reached the requirements of contract and design.
出处
《水力发电》
北大核心
2008年第5期79-80,共2页
Water Power
关键词
高强耐磨混凝土
硅粉混凝土
HF混凝土
施工质量控制
直孔水电站
high strength and abrasion-resistant concrete
siliceous concrete
HF concrete
construction quality control
Zhikong Hydropower Station