摘要
针对地下室后浇带渗漏问题,结合工程实例,阐述了工程后浇带渗漏的主要表现形式及其产生原因,对工程采用的压力灌浆法及施工技术措施进行了论述,并提出了施工质量控制措施,最后指出该方法均能满足补强防水的综合要求。
According to the leakage of the late poured band in the basement, the paper describes the main forms and the cause of the leakage of the late poured band combined with the engineering example, discusses the pressure grouting method and the construction technology, and puts forward the construction quality control measures, points out that the method meets the comprehensive requirements of the reinforcement waterproof.
出处
《山西建筑》
2008年第18期159-160,共2页
Shanxi Architecture
关键词
后浇带
止水灌浆
壁后灌浆
施工技术
late poured band, water-stop grouting, backwall grouting, construction technology