摘要
结合某地铁站工程的实际情况,介绍了支模工程的设计,并进行了验算,得出了该支模设计能保证使用安全的结论,最后提出了主要的施工技术措施,以保证地铁站工程的顺利进行,可供同类工程借鉴。
Combined with the real situation of one underground station project, it introduces the design of supporting mode project and gets the checking calculation, and deduces the conclusion that the supporting mode design can assure the safety of the utility, in the end it puts forward the main construction technical steps, to assure the trouble free operation of Underground station project, and it can be the reference to similar projects.
出处
《山西建筑》
2008年第18期304-306,共3页
Shanxi Architecture
关键词
地铁站
高支模
设计
施工
underground station, high supporting mode, design, construction