摘要
尼日利亚OML130区块是中海油在海外投资最大的开发项目,区内开发的第一个油田(AKPO130油田)平均作业水深为1500-1700m,这给油田钻完井作业带来了很大的挑战。针对AKPO130油田深水钻完井作业所面临的主要问题,分析了该油田深水钻完井方案及作业特点,并对今后我国海洋钻完井作业提出了一些建议。
The OML130 block in Nigeria is the largest development project invested by CNOOC overseas and the first oilfield in this block, AKPO130 oilfield is located at the water depth from 1 500 m to 1 700 m, which raised the great challenge for our drilling and completion operations. The drilling and completion program and the operation characters have been analyzed for the problems we encountered during deepwater operations in this field and also some thinking and suggestions have been put forwarded for CNOOC's deepwater drilling and completion in the future.
出处
《中国海上油气》
CAS
2008年第3期206-210,214,共6页
China Offshore Oil and Gas
关键词
AKPO130油田
深水钻完井
作业特点
思考与建议
AKPO130 oilfield
deepwater drilling and completion
operation character
thinking and suggestions