通过白山抽水蓄能电站拦污栅栅条、栅叶及水工整体等大比尺的结构模拟试验研究,分析拦污栅产生破坏的原因,对设计方案提出可供参考的建议。
Based on the large scale structural simulation tests of bar and body of the trash-rack in Baishan Pumped Storage Hydropower Station, the causation of the damage of the trash-rack is analyzed, and then some referential suggestions for the related design is put forward herein.
出处
《水利水电技术》
CSCD
北大核心
2008年第6期63-66,共4页
Water Resources and Hydropower Engineering
关键词
白山抽水蓄能电站
拦污栅
栅条
振动
模型试验
Baishan Pumped Storage Hydropower Station
trash-rack
rack bar
vibration
model test