结合实际工程对针梁式钢模台车的构造、工作原理、施工工艺流程、及施工管理等方面进行了介绍,着重分析了其使用中的优缺点,并对施工中出现的问题提出了解决措施。
According to the actual conditions of the project, the structure, principle, construction process, construction management, and other aspects of the steel-mould stair vehicles of needle bridge were introduced, focused on analysis of the use of its advantages and disadvantages, and the ways of solving problems in construction were put forward.
关键词
引水隧洞
混凝土衬砌
针梁式钢模台车
金盆水利枢纽
water-intake tunnel
concrete liner construction
steel-mould stair vehicles of needle bridge
Jin Pen Hydro- Complex.