三峡三期下游围堰爆破拆除起爆网路设计与可靠性分析 被引量:5

DESIGN AND RELIABILITY ANALYSIS OF INITIATING NETWORK FOR BLASTING DEMOTION OF THE 3RD STAGE DOWNSTREAM COFFERDAM OF THREE GORGES
下载PDF
导出
摘要 三峡三期下游围堰爆破拆除网路运用了非电复式交叉接力起爆网路。本文介绍了该工程起爆网路的设计,定量分析了单起爆点起爆同双起爆点起爆及单式加强网路、复式加强网路同复式交叉网路起爆可靠度差异,并建立了数学计算模型,供同类工程借鉴。 The non-electric double crossover relaying initiating network has been used in blasting demolition of the 3rd stage downstream cofferdam of Three Gorges.In the paper,the design of the initiating network for the engineering was introduced.This was followed by comparison of the reliability of different initiating networks,including single initiating spot and double initiating spots,single fortified initiating network,double fortified initiating network and double crossover initiating network.And the mathematic calculating models of these initiating networks were founded.These can be used as a reference for similar projects.
出处 《工程爆破》 2007年第3期68-72,共5页 Engineering Blasting
关键词 三峡工程 围堰 爆破拆除 起爆网路 可靠度 Three Gorges Engineering Cofferdam Blasting demolition Initiating network Reliability
  • 相关文献

参考文献6

二级参考文献13

共引文献33

同被引文献24

引证文献5

二级引证文献12

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部