高坝洲水利枢纽一期工程施工导流设计 被引量:1

Design of river diversion during first stage construction of GP
下载PDF
导出
摘要 高坝洲水利枢纽施工导流设计标准选用时,不仅考虑了长江水位顶托影响,还考虑了上游隔河岩调峰电站的运行方式改变了坝址处天然流量的实际情况。枯水时段施工导流建筑物设计标准选用的依据是可能的出库流量与隔—高区间流量相迭加,因而降低了一期低土石围堰的设计标准,但也带来了一些不利的影响。实践表明设计根据规范规定对上游水库提出的调蓄要求,对电站发电效益有所影响,由于在施工导流设计和工程建设过程中都由业主负责与有关方面进行协调,使问题得到妥善解决。 In selection of the standard for construction diversion of the Gaobazhou Project, not only the effect of the withstanding of water level in the Yangtze River but also the change in natural discharge at the damsite which results from the upstream Geheyan Hydropower Station’s operation of peak load regulation is taken into account. The design standard for diversion structure operating in low water period is based on superpositon of the possible discharge from the Geheyan reservoir and the regional discharge between Geheyan and Gaobazhou, so that design standard for the first stage earth and rockfill cofferdam is lowered. But this also brings about some adverse effect. The practice has proved that designing diversion structure in accordance with requirements stipulated in the norm for upstream reservoir storage will have a certain influence on the generation benefit of that upstream power station. These issues are basically settled through the project owner’s coordinating relations between related aspects in the course of diversion design and construction.
出处 《人民长江》 北大核心 1997年第9期34-36,共3页 Yangtze River
关键词 明渠导流 导流 水利枢纽 施工导流 Multi-phase diversion\ Channel diversion\ Design standard\ Vertical closure method\ Gaobazhou Project
  • 相关文献

同被引文献3

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部