摘要 南水北调中线穿黄隧洞的盾构始发深度大、地质条件差、地下水位高、始发空间狭小,始发进洞时涌水涌砂的风险很大。施工中制定了严密合理的工序,重点对始发区进行高喷和冷冻加固,安全顺利地实现了盾构始发。 Starting up construction technology with shield machine in the Yellow River Crossing Tunnel of the Middle Route Project of South-to- North Water Diversion was difficult because location was with great depth, poor geological conditions, high groundwater level, limited starting up space and risk in spraying sand and water. We developed strict and reasonable working processes and did high pressure concrete spraying as well as freezing consolidation on the important starting up area, at last we successfully realized safe starting up.
作者 于澎涛
出处 《南水北调与水利科技》 CAS CSCD 2008年第4期54-57,共4页 South-to-North Water Transfers and Water Science & Technology
关键词 穿黄隧洞 地基加固 盾构始发 Yellow River Crossing Tunnel foundation consolidation shield starting up
  • 相关文献

参考文献2

  • 1[1]张风祥,朱合华,傅德明.隧道盾构[M].北京:人民交通出版社,2004.
  • 2[2]南水北调中线一期穿黄工程联合项目组.南水北调中线一期穿黄工程初步设计报告[R].武汉:南水北调中线一期穿黄工程联合项目组,2004.