针对广州地铁五号线员村站—车陂南站区间盾构工程难点,对土压平衡盾构机在复合地层施工中出现的问题进行了分析研究,并提出了应对措施和处理思路,以期为类似地层施工提供参考借鉴。
Aiming at the engineering difficulty of shield from Yuancun station to Chepo station of subway No. 5 line in Guangzhou, the problem of earth pressure balance shield existed in mix ground construction was analyzed and studied, and the counter measurement and treatment ideas were provided, so as to provide references for .similar formation construction.
出处
《山西建筑》
2008年第23期312-313,共2页
Shanxi Architecture
关键词
盾构隧道
沉降监测
混凝土
塌方
shield tunnel, settlement monitoring, concrete, collapse