摘要
随着以三峡电站为代表的特大型水电站的陆续开工建设,电站与升压站的联系越来越重要,提供两者之间可靠、有效的跳闸信号传输通道,是保证电站安全运行的重要条件。文中对用长距离传输跳闸信号电缆容易引入干扰源的原因进行了分析,结合葛洲坝水电站工程改造的实践,提出用光纤通道代替长距离电缆传输跳闸信号。
Along with the construction of the Three Gorges Hydropower Plant as the representative of the super-sized hydropower stations, the relationship between hydropower stations and their booster stations become more and more important. Providing reliable, effective tripping signal transmission channel is an important condition to guarantee the safe operation of hydropower stations. The paper analyzes the reason that interference source is easy introduced by long-distance signal transmission cable, and combining with the engineering practice of the Gezhouba Hydropower Plant, the project of using fiber channel replacing long-distance signal transmission cable is proposed and realized.
出处
《水电自动化与大坝监测》
2008年第4期81-83,共3页
HYDROPOWER AUTOMATION AND DAM MONITORING
关键词
光纤通道
水电站
升压站
信号传输
跳闸
fiber channel
hydropower station
booster station
signal transmission
trip