摘要
湿法烟气脱硫系统是否设置GGH,是目前国内争议较大的问题,其对脱硫系统的投资和经济运行有重大影响。针对三水恒益电厂600 MW机组安装脱硝系统(SCR)之后,石灰石—石膏湿法烟气脱硫系统是否安装GGH进行了探讨,为工程初步技术设计提供参考。
The poinion of gas gas heater provided in the wet flue gas desulfurization system has big disputes in domestic at present. It has significant influence on the investment and economic operation of the desulfurization system. The installation of GGH on the FGD system with limestone - gypsum process after taking the denitrification device ( SCR ) of Hengyi Power Plant 600 MW units at Sanshui district has been discussed. It may provide reference for the similar FGD engineering preliminary design,
出处
《电力环境保护》
2008年第4期17-19,共3页
Electric Power Environmental Protection