水利工程施工期业主风险的多层次模糊综合评价研究 被引量:9

Study of the employer risk of hydraulic engineering in construction period by multilayer fuzzy comprehensive evaluation
下载PDF
导出
摘要 水利工程施工期的业主风险是影响工程质量和进度的重要因素。为保证新疆某水库引水西延干渠工程的顺利施工,对业主风险进行科学管理是非常必要的。研究过程中采用专家调查法分析得到工程施工期业主的风险因素清单,并建立多层次模糊综合评价体系进行评估论证,后以评价结果为依据,制定了科学的风险管理方案,采取多种措施进行风险控制和防范,保证了西延干渠工程施工建设的顺利进行。 The employer risk of hydraulic engineering in construction period is the crucial element that engineering quality and progress rate. To ensure the diversion channel project of a Xingjian' s reservoir affects the proceeding smoothly, it is necessary to manage the employer risk. In the process of study the expert inverstigation analysis method is used to obtain the owner's risk factor detailed list in the project construction period, and the multi-layer fuzzy synthetic evaluation system is established to carry on the appraisal proof. Based on the results of research, the science risk management plan is worked out, many kinds of measures are carried on the risk control and the guard, the west extended main channel project is on the advance of smooth construction.
出处 《水力发电学报》 EI CSCD 北大核心 2008年第4期141-145,共5页 Journal of Hydroelectric Engineering
基金 河南省基础与前沿技术研究计划项目(072300430230) 华北水利水电学院青年科研基金项目(HSQJ2004002)
关键词 水利工程 业主风险 层次分析法 风险分析 多层次模糊综合评价 hydraulic engineering employer risk analytic hierarchy process risk analysis muhilayer fuzzy comprehensive evaluation
  • 相关文献

参考文献2

二级参考文献7

  • 1[1]Cooper DF,CHAPPMAN CB.Risk analysis for large projects-models,methods and cases[M].John Wiley Sons,New York,1987.
  • 2[2]Mustafa MA,Al-Bahar JF.Project risk assessment using the analytic hierarchy process [J].IEEE Transaction on Engineering Management.1991,38(1):46-52.
  • 3[3]Charoenngam C,Yeh C Y.Contractual risk and liability sharing in hydropower construction [J].International Journal of Project Management,1999,17(1):29-37.
  • 4[4]CHAPMAN CB, DALE F COOPER.Risk Engineering Basic Controlled Interval and Memory Models[J].J Opl Res Soc 1983,134(1):51-60.
  • 5[5]CHAPMAN CB.A risk engineering approach to project risk management [J].Intermational Journal of ,Project Management,1990,18(1):5-16.
  • 6[6]CHAPMAN CB.Large Engineering Project Risk Analysis[J].IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT,1983,V26(1):51-60.
  • 7王振强,刘玉杰,于九如.SCERT在大型工程项目风险分析与管理中的应用研究[J].中国软科学,2002(7):105-108. 被引量:11

共引文献36

同被引文献38

引证文献9

二级引证文献29

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部