随着经济的快速发展,唐山电网负荷较重,较多的输、变电设备重载运行,使设备运行出现了一些新的问题,其中220 kV重载线路分裂导线鞭击的现象,值得设计、施工及运行单位研究并治理。
Along with the rapid development of economy, there's heavier load on Tangshan power system. The overload operation of more transmission and transformation power equipments caused new problems on running of the equipment. Here we discuss causes of 220 kV conducting wire collision and its countermeasure.
出处
《华北电力技术》
CAS
2008年第8期8-10,共3页
North China Electric Power
关键词
输电线路
导线鞭击
治理
transmission line
conducting wire collision
countermeasure