期刊文献+

新渭南高架车站桥梁钻孔灌注桩后压浆技术 被引量:6

Post-Grouting Techniques for Bored Piles of Bridges of New Weinan Elevated Railway Station
下载PDF
导出
摘要 郑西客运专线新渭南高架车站桥梁设计受桥上布置道岔的影响,对桥梁基础承载能力及工后沉降控制提出了更为严格的要求,为减少基础工后沉降、进一步提高基础承载能力,高架车站桥梁设计范围内采用钻孔灌注桩后压浆技术。 Affected by the arrangement of railway switches on the bridge decks, the more rigorous requirements were set for the carrying capacity and settlement control of the completed bridge foundations in the design of bridges of the New Weinan Elevated Railway Station on Zhengzhou-Xi'an Passenger Dedicated Railway. In order to reduce the settlement and to further raise the carrying capacity of the foundations, the post-grouting techniques for bored piles of the foundations were applied within the design range of the bridges of the Elevated Railway Station.
作者 陈应陶
出处 《桥梁建设》 EI CSCD 北大核心 2008年第4期78-81,共4页 Bridge Construction
关键词 钻孔灌注桩 后压浆技术 高架车站 客运铁路 bored pile post-grouting technique elevated railway station passenger railway
  • 相关文献

参考文献4

二级参考文献7

共引文献28

同被引文献44

引证文献6

二级引证文献42

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部