某基坑预应力管桩断桩事故的分析及处理 被引量:4

Analysis and Solution for Pile Broken Incident Caused by Excavation of Φ40m Silo Foundation Pit
下载PDF
导出
摘要 根据一座Φ40m圆库在基坑开挖时造成预应力管桩断桩事故的情况,分析了造成断桩的主要原因,提出了补救办法和加固过程中的注重防范的事项,总结了开挖淤泥质地基时避免断桩的五项具体控制措施,为解决和避免类似事故提供了参考。 By the details about prestressed pile broken incident which have occurred at the excavation of Φb40 silo foundation pit, with the analysis of the major element that lead to the incident, makes the proposal for reparation method and precaution measure in pile reinforcement, so afterwards defines 5 controUing provisions that can help avoid pile broken incident at the excavation of silt stratification and also can provide reference for solution of this incident.
作者 袁曙光
出处 《工程建设与设计》 2008年第8期43-46,共4页 Construction & Design for Engineering
关键词 基坑开挖 淤泥质地基 预应力管桩 断桩 管桩补强 foundation excavation silt stratification prestressedpile damagedpile pile reinforcement
  • 相关文献

参考文献6

  • 1GB50007-2002.建筑地基基础设计规范[S].[S].,..
  • 2JGJ94-94.建筑桩基技术规范[S].[S].,..
  • 3JGJ/T93-95.基桩低应变动力检测规程[S].[S].,..
  • 4GB50077-2003.钢筋混凝土筒仓设计规范[S].[S].,..
  • 5JGJ120-99.建筑基坑支护技术规程[S].[S].,..
  • 6JGJ/T8-97.建筑变形测量规程[S].[S].,..

共引文献3334

同被引文献13

引证文献4

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部