摘要
水电工程项目蓄水验收工作是水电站基本建设工程验收管理的重要环节。结合水电水利规划设计总院受托组织开展水电工程项目蓄水验收工作的实践,介绍了验收前应具备的条件、技术准备的要求和验收的工作程序,并提出了做好验收工作的意见和建议。
The acceptance work of water impoundment of hydropower project is an important link for the acceptance management of basic construction project of hydropower station. In combination with the practice of commissioned acceptance work for many hydropower projects organized by the Planning and Design General-Institute of Hydropower and Water Resources, this paper introduces the necessary conditions before acceptance, the requirements of technical preparation and the work procedures of acceptance, and then puts forward some ideas and suggestions for water storage acceptance.
出处
《水力发电》
北大核心
2008年第8期94-96,111,共4页
Water Power
关键词
蓄水验收
验收条件
实践
探讨
水电工程
water impoundment acceptance
condition for acceptance
practice
discussion
hydropower project