100m跨径架桥机节段拼装技术 被引量:1

Techniques for Sectional Assembling of Bridge Girder Erection Machines for 100 m Span Bridges
下载PDF
导出
摘要 目前跨度在100 m以上混凝土连续箱梁有支架法、挂篮悬浇、桥面吊机悬拼等施工方法。文章介绍的混凝土连续箱梁架桥机节段拼装施工技术,采用临时支墩施工方法,可将架桥机75 m标准跨径扩大至100~150 m范围,从而提供了除挂篮悬浇、桥面吊机拼装外的另一种新的施工工艺。 Concrete continuous box girders for spans of more than 100 m are normally constructed with the methods of scaffolding, concrete casting in suspension with hoisting cradles and assembling of deck cranes at high locations. The paper describes the technology for assembling bridge girder erection machines for installation of concrete continuous box girders. A temporary pier can be erected to extend a girder erection machine with a standard span of 75 m to 100 m - 150 m, thus providing a new technology for bridge construction in addition to the construction methods of concrete casting in suspension with hoisting cradles and assembling of deck cranes at high locations.
作者 林立华
出处 《中国港湾建设》 北大核心 2008年第4期39-45,共7页 China Harbour Engineering
基金 国家十五科技支撑计划项目(2006BAG04B03)
关键词 100m跨径 架桥机 节段拼装 临时墩 100 m span bridge girder erection machine sectional assembly temporary pier
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部