介绍了王家梁隧道的工程概况及地质情况,结合隧道的塌方情况,提出了管棚施工的加固方案,通过管棚施工过程深入探讨了YG50型钻机在大管棚施工中的应用,证明了该设备和工法的可行性。
It introduces the general situation and geology of Wangjialiang tunnel. Meanwhile, combimed with tunnel landslide, it puts forward the reinforcement plan of pipe shed construction. Through the pipe shed construction process, it discusses the application of YG50 driller in large pipe shed construction and proves the feasibility of this equipment and method.
出处
《山西建筑》
2008年第25期314-315,共2页
Shanxi Architecture
关键词
钻机
管棚施工
隧道
加固机理
driller, pipe shed construction, tunnel, reinforcement law