摘要
在工程实例的基础上,通过在施工过程对加固场地的周边路面沉降、浅层沉降、孔隙水压力、地下水位、土体深层水平位移等项目的监测,对超载预压排水固结法在软基处理中的过程控制及效果进行了分析。
Basing on the example,though supervising in the constructing process, including sedimentation around circumjacent road, sedimentation shallow, the press of interstice water,water table, the deep - seated tract in level displaceent, we analyze the controlling process and effect in basal software disposal on overweighed pre - suppress draining concretion method.
出处
《城市勘测》
2008年第4期154-157,共4页
Urban Geotechnical Investigation & Surveying
关键词
软基处理
超载预压排水固结法
监测
效果
soft clay foundation treatment
overweighed pre - suppress draining concretion method
monitor
effect