摘要
为了解决型钢混凝土结构在施工过程中,工序穿插繁杂且相互制约、施工速度慢、协调难度大等问题.笔者通过工程实例,对型钢混凝土梁柱节点的施工深化设计、吊装方案的优化、施工机械的合理选择提出了建议,并对各施工工序之间的关系进行了科学的调整,压缩了工序间的时间间歇,加快了施工进度.
In order to solve the difficulties including complex and mutual restrictive process,low velocity of SRC structure constructions, detailed constructional design of column-beam joints in SRC are made with the adopted optimized lifting plan and reasonable selection of construction machines, scientific adjustment are also made among different construction processes, in order to condense construction alternation and accelerate the construction speed.
出处
《青岛理工大学学报》
CAS
2008年第4期120-123,共4页
Journal of Qingdao University of Technology
关键词
型钢混凝土
施工工艺
约束事件
SRC
construction technologies
restrict events