摘要
通过对大唐信阳二期2×600 MW级超超临界机组工程主厂房布置格局、结构尺寸的优化设计,分析比较了不同布置方案对初投资、运行维护的影响。大唐信阳二期的主厂房布置方案在满足运行维护要求的前提下,可比容积达到了0.186m3/kW的先进水平,其优化设计的经验可供类似工程参考。
Based on optimized design of main power block configuration and structural sizes for Datang Xinyang 2×600 MW USC units project, phase II, the paper analyzes and compares the affects of different arrangement schemes on the primary investment, operation and maintenance. The main power block configuration scheme of Datang Xinyang, phase II project has reached advanced level of 0.186 m^3/kW comparable volume in conditions to meet the operation and maintenance requirements. Its design experiences can be referred for other similar projects.
出处
《电力建设》
2008年第9期64-67,共4页
Electric Power Construction
关键词
主厂房布置
优化设计
单框架
体积指标
main powerblock configuration
optimized design
single frame
volumetric index