介绍500 kV武东变电站"两型一化"建设施工总体思路及实施情况。特别是电缆沟压顶及沟盖板工厂化加工、ALC装配式围墙及防火墙、构支架钢模板新技术等,充分体现了"两型一化"的工作思路。
The general thinking and its carrying out condition of constructing the 500 kV Wudong aubstation with "Two Patterns One Popularization"were introduced. Especially the new technologies such as:factory assembly of coping and coping for cable trenches, ALC fabricated wall and fire wall, framework with new technol- ogy etc,fully embodied the working idea of "Tow Patterns One Popularization".
出处
《湖北电力》
2008年第4期42-43,共2页
Hubei Electric Power
关键词
变电站
两型一化
电力电缆
substation
"Tow Patterns One Popularization"
power cable