在投产不久的时间内,广东金湾发电厂两台炉磨煤机的石子煤斗进料管经常发生堵管,通过对石子煤斗进行改造,加强冲渣,消除了堵管问题。
The feed pipe was always chocked up at the cobble coal bunkers of two pulverizers in Guangdong Jinwan power plant before long its putting into production. Through its modification and cinder flushing, the plugging phenomenon was solved.