结合工程概况,介绍了临时路面设计方案实施的困难,对军用梁临时路面系统的变更进行了设计,并对变更方案进行了具体的结构检算,综合计算分析以及通车证明,军用梁临时路面系统安全可靠。
Combining the construction' s general situation, the paper introduces the difficulties of implementing the temporary pavement design scheme, design the changes of the temporary pavement system of the military girders, and has a structural calculation on the change scheme, furthermore, it proves the safety and reliability of the temporary pavement system of the military girders by the comprehensive calculating analysis and its evidence for opening to traffic.
出处
《山西建筑》
2008年第26期267-268,共2页
Shanxi Architecture
关键词
盖挖段
军用梁
临时路面系统
结构检算
top-down section, military girders, temporary pavement system, structural calculation