丹江口大坝加高工程右岸转弯坝段横向锯缝施工 被引量:2

Horizontal Saw Seam Construction at Dam Turning Section on Right Bank of Danjiangkou Dam Heightening Project
下载PDF
导出
摘要 丹江口水利枢纽右岸混凝土坝转弯坝段在平面上呈凸向下游的反弧形,初期工程中横缝进行了灌浆。在气温影响下,夏季坝体被挤压向下游变形,坝基上游端部受拉,扬压力增大;冬季挤压消失、变形恢复常态。为消除转弯坝段长期因受温度周期性变化而产生的坝体稳定及应力不利的变形,大坝加高前采取了消除横缝间连接的锯缝施工方案,解决了转弯坝段反向变形问题,施工取得了良好效果。 Concrete dam turning section on right bank of the Danjiangkou Dam Project shows anti-arc shape of convex to the downstream on the plane, Influencing by temperature, the dam was squeezed to the lower reaches of deformation in summer, deformation restored normality in winter. In order to eliminate deformation of darn turning section because of cyclical changes of temperature, saw seam construction program of eliminating link between the joints was taken before heightening darn, resolving problem of reverse deformation of the dam turning section, the construction has achieved good results.
作者 王亚菊
出处 《南水北调与水利科技》 CAS CSCD 2008年第5期77-79,共3页 South-to-North Water Transfers and Water Science & Technology
关键词 转弯坝段 反向变形 坝体横缝 锯缝施工 dam turning section reverse deformation dam joints saw seam construction
  • 相关文献

参考文献2

  • 1[1]长江水利委员会长江勘测设计研究院.丹江口水利枢纽大坝加高工程初步设计报告(修订本)[R].武汉:长江水利委员会长江勘测设计研究院,2004.
  • 2[3]NSBD6-2006,南水北调中线一期丹江口水利枢纽混凝土坝加高工程施工技术规程[S].