摘要
该文介绍了至界岭隧道穿越层状围岩段,采用锚喷支护、辅以超前锚杆进行临时支护的方法。按照弱爆破、短进尺、早支护、勤量测的原则施工,获得成功,可供类似施工参考。
The article introduces Zhijielin Tunnel crossing the layered country rock section by the temporary supporting method of anchoring spray attached with the leading anchor rod. The tunnel is successfully constructed according to the principle of weak demolition, short tunneling, early supporting and frequent measuring able to provide the reference for the similar construction.
出处
《城市道桥与防洪》
2008年第9期77-79,共3页
Urban Roads Bridges & Flood Control
关键词
隧道
层状围岩
施工
tunnel, layered country rock, construction