团城铁矿残矿回采工程支护方法试验研究 被引量:3

Supporting method for residual ore extraction at Tuancheng iron mine
下载PDF
导出
摘要 团城铁矿100m水平以下矿体遭到民采空区严重破坏,采用在活动空区边缘出矿的方法回收冒落残矿,试验研究了多种支护方法,最终用U型支架,通过合理设计支架结构与优选支架尺寸,解决了高应力、大变形巷道支护的技术难题,使团城铁矿50m水平之上的残留矿量得到了合理回采,取得了良好的技术经济效果。 The ore body below I00m level was almost destroyed by the mined-out area in Tuaneheng i- ron mine and the method of ore drawing from the boundary of caved area was adopted for recovery of the remnant ore. Experimental Studying on many support methods, U-shape frame has been used to Move the problems of supporting the gateway with high stress and large deformation by means of the rational structure design and the optimal size. The remnant ore in the mined area is reasonable stoping above 50 m level, and has achieved good technical and economic efficiencies.
作者 任凤玉 王燕
出处 《中国矿业》 北大核心 2008年第8期66-68,共3页 China Mining Magazine
关键词 采空区 残留矿柱 巷道支护 U型支架 mined area residual pillar gateway support U-shaped frame
  • 相关文献

参考文献1

  • 1任凤玉,韩志勇,隋金铂,等.回收巷道过散体层试验研究[R].邯郸:团城铁矿空区安全与残采技术科研组,2003.

同被引文献22

引证文献3

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部