摘要
钢桁架栈桥是热电站输煤栈廊的重要组成部分,根据在施工实践中的体会,文章主要介绍热电站输送机走廊钢桁架栈桥的施工工艺,以及施工过程中钢桁架的制作,拼装,吊装,焊接等主要工序的施工措施.
The steel truss bridge is an important part of the stack gallery used to transport coat tor a mermal power station. According to the experience during construction, the essay is written about the technology of constructing a steel truss bridge for a thermal power station, and some construction measures of main process like production, assembly, hoisting, welding and so on.
出处
《吉林建筑工程学院学报》
CAS
2008年第3期57-60,共4页
Journal of Jilin Architectural and Civil Engineering
关键词
钢桁架
制作工艺
吊装
控制措施
steel truss
manufacturing technology
hoisting
control measures