摘要
针对复杂的风/光互补发电场优化设计问题,首次提出了一种新的风/光互补发电场优化设计模型。在分析了现有研究的基础上,给出了适合于风/光互补发电场部件发电量计算的计算模型,归纳了设计时各部件的数量和类型选择的约束关系,最后综合给出了一种新的适合于风/光互补发电场优化设计的模型。
To solve the complex optimization problem of wind/solar hybrid generation plant design, a new optimal design computation model of wind/solar hybrid generation plant design is given for the first time. Based on the analysis of previous research, component power output computation model is put forward, then constraint relationship of components' types and number is induced. At last, a suitable optimization design model of wind/solar hybrid generation plant is brought out.
出处
《计算机工程与设计》
CSCD
北大核心
2008年第18期4836-4838,共3页
Computer Engineering and Design
基金
国家自然科学基金重点项目(60534040)
广州省自然科学基金重点项目(05001819)