摘要
对目前采用井筒外部固井工艺建造的高压储气井进行了应力分析,指出了其存在的安全隐患。提出了采用内插管正循环固井工艺建造储气井的方法,从而消除安全隐患,确保CNG加气站的安全运行,为建造高压储气井提供借鉴。
At present, for the high pressure storage gas well built with technology of well cementation out of the pipe, a stress analysis was made. We pointed out that it has hidden danger in safety, and put forward a technology of building a storage gas well, which is cemented by insideinsert pipe in direct circulation. Thus, the hidden danger will be eliminated and CNG gas station operation is ensured safe, and the human life and property in safety around the station are protected. It gives a typical example for building a high pressure storage gas well.
出处
《石油矿场机械》
2008年第9期97-100,共4页
Oil Field Equipment
关键词
CNG
储气井
固井工艺
应力分析
CNG
storage gas well
well cementation technology
stress analysis